Risk Analysis of the River Diversion Under Construction of Cascade Hydropower Stations[J]. Advanced Engineering Sciences, 2014,46(1):75-80. DOI: 10.15961/j.jsuese.2014.01.016.
Abstract:The temporal distribution of the flood of the hydropower station can be altered when the upstream hydropower station is constructed synchronously
which may lead to the inapplicability of current diversion risk estimation method.Considering the hydrologic uncertainty of diversion system
a system risk analysis model was established based on risk analysis theory. In view of the correlation between the sectional flood of upper hydropower station and interval-basin flood
the Copula function was used to establish the joint probability distribution
and each flood process was simulated in following by using Monte Carlo method. On this basis
the construction flood of hydropower station was calculated by coupling the simulation of the cofferdam-break flood
routing of river flood and composition of regional flood. Subsequently the system risk was obtained. An engineering case was presented to validate the applicability of the proposed model. And the sensitivity analysis of other risk factors was performed. Additionally
the effect of upper hydropower station on diversion risk was investigated.The study could offer a referential basis for establishment of the diversion standard under the construction of cascade power stations.
关键词
施工导流风险分析Copula函数Monte Carlo溃堰联合分布
Keywords
construction diversionrisk analysisCopula functionMonte Carlocofferdam breakjoint probability distribution