an improved method for scheduling arrival aircrafts at an airport with multiple runways was studied. Scheduling arrival aircrafts is a typical non linear combinatorial optimization problem
and the application of genetic algorithm to this problem was explored.A sequence of aircrafts was a chromosome. We designed the crossover operator and mutation operator. In decoding phase
first we assigned the runway
then we used the improved moving method to remove the conflict between aircrafts
insert idle time
decide the sequence and time of aircrafts landing. The simulation result demonstrated that the presented algorithm can assist controllers to make decisions.
关键词
遗传算法到达飞机调度空闲时间
Keywords
genetic algorithmsscheduling arrival aircraftsidle time
Beasley J E,Sonander J,Havelock P.Scheduling aircraft landings at London Heathrow using a population heuristic[J].Journal of the Operational Research Society,2001,52:483-493.
Cheng V H L,Crawford L S,Menon P K.Air traffic control using genetic search techniques[C]//Proceedings of the 1999 IEEE International Conference on Lontrol Applications,1999,1:249-254.
John E.Fuzzy reasoning-based sequencing of arrival aircraft in the terminal area[C]//AIAA Guidance,Navigation and Control Conference,New Orleans,LA,1997:1-11.
Xu Xiaohao,Huang Baojun.Study of fuzzy integrated judge method applied to the aircraft sequencing in the terminal area[J].Acta Aeronautica et Astronautica Sinica,2001,22(3):259-261.[徐肖豪,黄宝军.终端区飞机排序的模糊综合评判方法研究[J].航空学报,2001,22(3):259-261.]
Beasley J E,Krishnamoorthy M,Sharaiha Y M,et al.Displacement problem and dynamically scheduling aircraft landings[J].Journal of the Operational Research Society,2004,55:54-64.
Baker K R,Scudder G D.Sequencing with earliness and tardiness penalties:A review[J].Operations Research,1990,38(1):22-36.
周明,孙树栋.遗传算法原理及应用[M].北京:国防工业出版社,2002.
Mazzini R,Armentano V A.A heuristic for single machine scheduling with early and tardy costs[J].European Journal of Operational Research,2001,128:129-146.
Lee C Y,Choi J Y.A genetic algorithms for job sequencing problems with distinct due dates and general early-tardy penalty weights[J].Computers and Operations Research,1995,22(8):857-869.